1.6 TPH LABSA & SLES|Europe Site · Installation Inspection & Pre-Commissioning Punch List Rectification

Nov 26, 2026

This week, our technical team completed on-site verification of the installation of rotating and static equipment, process piping, instrumentation, electrical facilities and PLC systems for the 1.6 TPH LABSA & SLES unit.

All non-conforming items have been logged item by item and submitted to the client for rectification. Close tracking will be maintained until all punch items are closed out to prepare for subsequent commissioning.💪

 